Dropped kerbs in Westmorland and Furness

What Westmorland and Furness Council charges, its rules for driveways, and where to apply.

Application
£348
2026-27
Min. depth
5m

Tap a figure for its source, fee year and the date we checked it.

Work out my costs

Westmorland and Furness's fees

Along the kerb, including the sloping kerbs at each end. Optional.
Crossing width × pavement width, if you know it. Optional.
Anything else?

Westmorland and Furness Council

A contractor from the council's approved list builds it

You pay at least£348

The council doesn't say whether VAT is included.

Plus

  • Building the dropped kerb: not published by the council
  • Application fee
    £348
    • Per individual residential property (vehicle access permit)
    • VAT not stated
    westmorlandandfurness.gov.uk, checked 15 November 2026 · Fee year 2026-27
    The council's words
    “Vehicle Access (individual residential property) £348”
  • Building the dropped kerb
    Not published by the council

Refunds

The council doesn't say whether the application fee is refunded.

Other charges the council lists

These may or may not apply to you, so they aren't in the total.

  • Vehicle access permit: multiple properties and commercial use
    £972
    • Per application (multiple properties and commercial use)
    • VAT not stated
    westmorlandandfurness.gov.uk, checked 15 November 2026 · Fee year 2026-27
    The council's words
    “Vehicle Access (multiple properties and commercial use) £972”
  • Change of contractor
    £45.70
    • Per change of contractor after the permit is issued
    • VAT not stated
    westmorlandandfurness.gov.uk, checked 15 November 2026 · Fee year 2026-27
    The council's words
    “Change of contractor £45.70”
  • Re-activation of an existing permit
    £45.70
    • Per re-activation of an existing permit
    • VAT not stated
    westmorlandandfurness.gov.uk, checked 15 November 2026 · Fee year 2026-27
    The council's words
    “Re-activation of a an existing permit £45.70”

Westmorland and Furness's rules

  • Depth of your driveway

    The council's minimum is 5m.

    The council's words
    “We are unable to consider applications for a vehicle crossing unless the length of the drive is a minimum of 5m.”
    westmorlandandfurness.gov.uk, checked 15 November 2026

Other layout rules

Off-road driveway at least 5m measured from the private boundary to the building, so a vehicle fits wholly within the drive. Drive surfaced in bituminous, cement-bound or otherwise bound material (block paving or 2 rows of flags allowed) for at least 5m inside the site; no loose gravel or slate chippings within 5m of the highway. No surface water onto the highway (crossfall, permeable surface or channel drainage to a drain/soakaway). The crossing will not be authorised until the driveway is completed.

westmorlandandfurness.gov.uk, checked 15 November 2026

Lamp posts and street furniture

The Street Lighting Team considers proposals near a street lighting column and advises if it must be repositioned; columns are very costly to move and, if moving is possible, the applicant pays.

westmorlandandfurness.gov.uk, checked 15 November 2026

Driving over the kerb without permission

It is an offence under S131 of the Highways Act 1980 to excavate in the highway without a permit. If the crossing is not completed by the end of the agreed works or is not suitable for adoption, the council may execute or alter the works and recover the expenses. No statement found about driving over a kerb without a crossing.

westmorlandandfurness.gov.uk, checked 15 November 2026

When the council says you need planning permission

  • Access constructed on an A, B or C class road
  • Property is a new build
  • Changing the use of your garden to a driveway
See all 7 conditions
  • Surfacing over an area greater than 5 square metres (unless using permeable material)
  • Access passes over land registered as common land or a village green
  • Removing the grass strip in front of the property
  • Property in a conservation area, subject to an Article 4 Direction, or with permitted development rights removed (planning guidance page)
westmorlandandfurness.gov.uk, checked 15 November 2026

Check your driveway against these rules

From your house to the back of the pavement.
The same width as in the cost calculator above.
Type of crossing
Is your house on a classified road (an A, B or C road)?
Is it in a conservation area, or a listed building?

Enter your measurements to check them against Westmorland and Furness Council's rules.

  • Depth of your drivewayEnter your depth to check

    The council's minimum is 5m.

    “We are unable to consider applications for a vehicle crossing unless the length of the drive is a minimum of 5m.”
    westmorlandandfurness.gov.uk, checked 15 November 2026
  • Conservation area or listed buildingTell us if this applies to you
    “Property in a conservation area, subject to an Article 4 Direction, or with permitted development rights removed (planning guidance page)”
    westmorlandandfurness.gov.uk, checked 15 November 2026

Applying to Westmorland and Furness

Who builds it
A contractor from the council's approved list builds it
westmorlandandfurness.gov.uk, checked 15 November 2026
How long it takes
Give at least four weeks' notice before you plan to start the work. A compliance officer inspects after the application is received; if approved, the council contacts the contractor for a start date and issues the permit before it.
westmorlandandfurness.gov.uk, checked 15 November 2026
Approved contractors
The council's list

Apply on the council's website

Sources

Every page we used from Westmorland and Furness Council's website, checked on 15 November 2026.