Westminster's fees

Along the kerb, including the sloping kerbs at each end. Optional.
Crossing width × pavement width, if you know it. Optional.
Anything else?

City of Westminster

The council builds it

You pay at least£142

Figures include VAT.

Plus

  • Building the dropped kerb: 15% of the crossover works estimate (the guidance does not spell out the base) plus the estimated cost of the works from the schedule of rates of the council's approved contractors and an allowance for contingencies; remeasured on completion with any difference refunded or charged
  • Application fee
    £142
    • Per application (assessment only)
    • Including VAT
    westminster.gov.uk, checked 15 November 2026 · No fee year stated · Page updated 14 March 2025
    The council's words
    “The application fee is £142 including VAT.”
  • Building the dropped kerbFormula
    15% of the crossover works estimate (the guidance does not spell out the base) plus the estimated cost of the works from the schedule of rates of the council's approved contractors and an allowance for contingencies; remeasured on completion with any difference refunded or charged
    • Per crossover (estimate)
    • VAT not stated

    Not included in the total

    westminster.gov.uk, checked 15 November 2026 · No fee year stated
    The council's words
    “This estimate will include an allowance for contingencies and a 15% administration fee to cover the costs incurred by the Council.”

Refunds

The application fee is not refunded if your application is refused.

westminster.gov.uk, checked 15 November 2026 · No fee year stated
The council's words
“which should be returned to the address below together with £142 non-refundable application fee”

Westminster's rules

  • Depth of your driveway

    The council's minimum is 4.8m.

    The council's words
    “must be of a minimum size of 4.8metres (16ft) in length by 2.4metres (8ft) in width”
    westminster.gov.uk, checked 15 November 2026

Other layout rules

Off-street parking space at least 4.8m long by 2.4m wide; access must not involve manoeuvres dangerous to the public; gates must not open onto the highway (including the footway); crossovers are built with a crossfall to the road and the occupier must tie in levels on private land. The council will normally resist car parking on front gardens and frontages, and vehicular access to it, particularly where it would lose on-street parking; applicants should first ask Planning whether an off-street parking area can be built.

westminster.gov.uk, checked 15 November 2026

When the council says you need planning permission

  • access onto a classified road
  • demolishing or altering a forecourt wall of at least one metre high
  • property other than a single family dwelling house (flats or other uses)
See all 5 conditions
  • alterations to the premises needed to build and use the crossover
  • change of planning use of the forecourt/front garden
westminster.gov.uk, checked 15 November 2026

Check your driveway against these rules

From your house to the back of the pavement.
The same width as in the cost calculator above.
Type of crossing
Is your house on a classified road (an A, B or C road)?
Is it in a conservation area, or a listed building?

Enter your measurements to check them against City of Westminster's rules.

  • Depth of your drivewayEnter your depth to check

    The council's minimum is 4.8m.

    “must be of a minimum size of 4.8metres (16ft) in length by 2.4metres (8ft) in width”
    westminster.gov.uk, checked 15 November 2026
  • Classified (A, B or C) roadTell us if this applies to you
    “access onto a classified road”
    westminster.gov.uk, checked 15 November 2026

Applying to Westminster

Who builds it
The council builds it
westminster.gov.uk, checked 15 November 2026
How long it takes
Reply to the application within 3 weeks; operations estimates and Traffic Regulation Orders take considerably longer (TMO up to six months if no objections). Works programmed within six weeks of payment, or about 28 days after parking is re-designated where bays exist.