Dropped kerbs in Hillingdon
What London Borough of Hillingdon charges, its rules for driveways, and where to apply.
- Min. depth
- 3.8m
Tap a figure for its source, fee year and the date we checked it.
Hillingdon's fees
London Borough of Hillingdon
The council builds it
You pay at least£428
No VAT applies.
Plus
- Building the dropped kerb: 5% of cost of the works plus the cost of the works, estimated from the council's agreed schedule of rates with its term service contractor (quote after inspection, valid 90 days)
- Application fee£164
- Per resident application (administration fee)
- No VAT
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle crossing application fee (non- R 149.00 163.90 NB 164.00 10.1% 180.00”
- Inspection fee£264
- Per crossing (supervision fee, resident)
- No VAT
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle crossing supervision Fee R 240.00 264.00 NB 264.00 10.0% 290.00”
- Building the dropped kerb5% of cost of the works plus the cost of the works, estimated from the council's agreed schedule of rates with its term service contractor (quote after inspection, valid 90 days)
- Per crossover (resident)
- No VAT
Not included in the total
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle Crossings contstruction fee R At cost plus 5% N/A NB At cost plus 5%”
Refunds
The application fee is not refunded if your application is refused.
The council's words
“Applicants will be charged a non-returnable highway administration/application fee for processing their crossover application”
Other charges the council lists
These may or may not apply to you, so they aren't in the total.
- Vehicle crossing application fee (non-resident)£180
- Per non-resident application
- No VAT
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle crossing application fee (non- R 149.00 163.90 NB 164.00 10.1% 180.00”
- Vehicle crossing supervision fee (non-resident)£290
- Per crossing
- No VAT
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle crossing supervision Fee R 240.00 264.00 NB 264.00 10.0% 290.00”
- Vehicle crossings construction fee (as part of planned works)75% of cost of the works
- Per crossover (resident, built with planned works)
- No VAT
modgov.hillingdon.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“Vehicle Crossings contstruction fee (as part of planned works) R At 75% cost N/A NB At 75% cost”
Hillingdon's rules
Depth of your driveway
The council's minimum is 3.8m.
The council's words
“A crossover may be offered where the frontage is an absolute minimum of 3.8 metres deep (for parking at 90 degrees to the carriageway)”
pre.hillingdon.gov.uk, checked 15 November 2026Minimum width (single crossing)
Council limit: 2.4m, measured at your property boundary.
The council's words
“A single width crossover must be a minimum of 2.4 metres wide at the back of the footway.”
pre.hillingdon.gov.uk, checked 15 November 2026Maximum width (shared crossing)
Council limit: 5m, measured along the kerb.
The council's words
“a maximum of 5m flat section will be allowed for each new crossover”
pre.hillingdon.gov.uk, checked 15 November 2026
Width, in the council's words
“The crossover width may be widened to match the width of the hardstanding up to a maximum width of 5m or 50% of the width of the frontage of the property (whichever is greater).”
“Where applicants require extensions to existing crossovers, the total width must not exceed 5m flat section.”
Other layout rules
Standard hardstanding 4.8m deep at 90 degrees to the carriageway; short-frontage minimum 3.8m deep with no overhang; shared crossovers may be approved with a frontage at least 3.2m deep and 9m wide. On classified roads vehicles must enter and exit in forward gear. Not within 5m of a roundabout or junction (applied to all classified roads; case by case on residential roads); not within 10m of traffic signals, pedestrian/zebra crossings or School Keep Clear markings; not within 10m of a bus stop flag (20m where more than one bus service). Pedestrian visibility splays 2.4m x 2.4m with walls/fences/shrubs kept to 0.6m; carriageway visibility X 2.4m, Y 43m (30mph) or 33m (20mph). Gates must open inwards. A low (up to 0.6m) wall, fence or landscaping must block the rest of the frontage. Only one crossover per property; a second needs a frontage at least 12m wide, forward-gear in/out and room to park 5m between accesses. Verges/amenity areas: may be permitted where less than 4m from kerb line to property threshold. Hardstanding must be permeable or drain within the site (otherwise planning permission). Domestic crossovers are for vehicles up to 3.5 tonnes.
Trees
May be refused if excavation disturbs a highway tree's root protection zone (4 x trunk circumference at 1.5m). Tree Officer site visit and report charged to the applicant; a trial excavation may be required at the applicant's cost, and the crossover is refused if roots over 25mm are found. If the tree officer agrees removal, the applicant pays for removal and a replacement highway tree; trees planted within the last two years may be relocated at the applicant's expense.
Lamp posts and street furniture
Crossovers should be at least 1m from lamp columns or other street furniture; otherwise the applicant pays to reposition it, and the crossover may be refused if no alternative location exists. Utility covers/apparatus alterations are at the applicant's cost. Traffic calming relocated only in exceptional circumstances with road safety team approval, at the applicant's cost.
Driving over the kerb without permission
Driving over the footway without a crossover is an offence under s184 Highways Act 1980; the council also uses s16 London Local Authorities and Transport for London Act 2003. A 21-day compliance period is issued before bollards or barriers are installed; repair costs are recovered from the owner/occupier. Vehicles overhanging the footway face action under s137 Highways Act. Crossovers breaching the policy may be removed at the resident's cost.
When the council says you need planning permission
- Vehicle access leads directly onto a classified road (A, B or C road)
- Listed building
- Property other than a single-family dwelling, e.g. flat, maisonette, commercial or industrial premises
See all 7 conditions
- Works include demolition of a front wall more than 1 metre high
- House in multiple occupation
- Property within a new development
- Parking area over 5 sq m that does not meet the Government's minimum drainage requirements
Check your driveway against these rules
Enter your measurements to check them against London Borough of Hillingdon's rules.
- Depth of your drivewayEnter your depth to check
The council's minimum is 3.8m.
“A crossover may be offered where the frontage is an absolute minimum of 3.8 metres deep (for parking at 90 degrees to the carriageway)”
pre.hillingdon.gov.uk, checked 15 November 2026 - Minimum width (single crossing)Enter your width to check
Council limit: 2.4m, measured at your property boundary.
“A single width crossover must be a minimum of 2.4 metres wide at the back of the footway.”
pre.hillingdon.gov.uk, checked 15 November 2026 - Classified (A, B or C) roadTell us if this applies to you
“Vehicle access leads directly onto a classified road (A, B or C road)”
pre.hillingdon.gov.uk, checked 15 November 2026 - Conservation area or listed buildingTell us if this applies to you
“Listed building”
pre.hillingdon.gov.uk, checked 15 November 2026
Applying to Hillingdon
- Who builds it
- The council builds itpre.hillingdon.gov.uk, checked 15 November 2026
- How long it takes
- 'We aim to process and reply to each application within 10 to 15 working days of receiving it.' Estimate valid 90 days. 'The aim is for crossovers to be constructed within 8 weeks of receipt of payment.'pre.hillingdon.gov.uk, checked 15 November 2026
Sources
Every page we used from London Borough of Hillingdon's website, checked on 15 November 2026.
- https://pre.hillingdon.gov.uk/dropped-kerbs
- https://pre.hillingdon.gov.uk/dropped-kerbs/applying
- https://pre.hillingdon.gov.uk/dropped-kerbs/guidance-notes
- https://pre.hillingdon.gov.uk/dropped-kerbs/application-process
- https://pre.hillingdon.gov.uk/parking/enforcement-dropped-kerbs
- https://pre.hillingdon.gov.uk/downloads/file/2423/domestic-vehicle-footway-crossover-policy
- https://modgov.hillingdon.gov.uk/documents/s65764/Appendix%20H1%20-%20Fees%20and%20Charges%202026-27.pdf
- https://pre.hillingdon.gov.uk/xfp/form/355