Dropped kerbs in Bolton
What Bolton Metropolitan Borough Council charges, its rules for driveways, and where to apply.
Tap a figure for its source, fee year and the date we checked it.
Bolton's fees
Bolton Metropolitan Borough Council
The council builds it
You pay at least£47
The council doesn't say whether VAT is included.
Plus
- Building the dropped kerb: no fixed price (the council only gives a guide)
- Application fee£47
- Per site inspection (paid when asking for a firm price)
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“There is a non-refundable fee for this inspection of £47.00”
- Building the dropped kerbNot a price: the council's rough guide is about £1,301
- Per new 4.5m (5 kerbstone) crossing, Measurement B up to 2.5m (typical cost)
Not included in the total
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“4.5 (5 kerbstones) up to 2.5 £1301”
Refunds
The application fee is not refunded if your application is refused.
The council's words
“There is a non-refundable fee for this inspection of £47.00 but should you then carry out the works this fee will be deducted from the overall cost.”
Other charges the council lists
These may or may not apply to you, so they aren't in the total.
- H bar marking over 6 metres£150
- Per H bar marking over 6m
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“The cost is £120 for a marking up to six metres in length and £150 for a marking over six metres.”
- Utility cover alteration: stop valve/water meter box£40.50
- Per cover
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“Stop valve/water meter box < 200mm x 200mm £40.50”
- Utility cover alteration: fire hydrant£64
- Per cover
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“Fire Hydrant < 400mm x 400mm £64”
- Utility cover alteration: manhole cover£120
- Per cover
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“Manhole Cover < 600mm x 600mm £120”
- Utility cover alteration: Openreach/Virgin box£2,252
- Per box
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · No fee year statedThe council's words
“Openreach/Virgin box £2252”
- Section 50 / street works licence Type 1 (incl. construction of a new vehicular crossing)£588
- Per licence (agreed works duration)
- VAT not stated
bolton.gov.uk, checked 15 November 2026 · Fee year 2026-27The council's words
“TYPE 1 Works undertaken on the public highway not involving the installation of apparatus under the SA01 £588.00”
Bolton's rules
Depth of your driveway
The council's minimum is 4.8m.
The council's words
“An off road driveway has to be constructed with a minimum of 4.8 metres between the back of the footway and the building”
bolton.gov.uk, checked 15 November 2026
Other layout rules
Driveway must be built before requesting the crossing. Drive should fall to the kerb at about 1:40 (approx. 1 inch per m). No dropped kerb within a lay-by. Crossing is for private or light goods motor cars. Typical-cost table covers crossings of 4.5m to 8.3m (5 to 9 kerbstones); other sizes priced individually. No maximum width stated.
Trees
If there is a tree outside the house or where the crossing is wanted, contact streetcare@bolton.gov.uk; a highway tree in the way needs further discussion of programming and costs.
Lamp posts and street furniture
Street lighting columns/furniture near the crossing: contact streetcare@bolton.gov.uk. They are very costly to move and, if moving is possible, the applicant pays (including the electricity company's disconnection/reconnection costs). Utility cover alterations are charged separately (shown under the council's other charges).
When the council says you need planning permission
- Access is from an A, B or C classified road
- Crossing is connected to works inside the site that need planning permission, e.g. paving over a former garden area, building a new house or garage, or changing the use of the property (get written confirmation from planning.control@bolton.gov.uk before work starts)
Check your driveway against these rules
Enter your measurements to check them against Bolton Metropolitan Borough Council's rules.
- Depth of your drivewayEnter your depth to check
The council's minimum is 4.8m.
“An off road driveway has to be constructed with a minimum of 4.8 metres between the back of the footway and the building”
bolton.gov.uk, checked 15 November 2026 - Classified (A, B or C) roadTell us if this applies to you
“Access is from an A, B or C classified road”
bolton.gov.uk, checked 15 November 2026
Applying to Bolton
- Who builds it
- The council builds itbolton.gov.uk, checked 15 November 2026
- How long it takes
- 'Work can start up to 12 weeks from date of cleared payment', typically 1 to 3 days on site; longer where utility covers or lighting columns must move.bolton.gov.uk, checked 15 November 2026
- Apply
- Not published by the council
Sources
Every page we used from Bolton Metropolitan Borough Council's website, checked on 15 November 2026.
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/2
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/3
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/4
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/5
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/6
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/7
- https://www.bolton.gov.uk/roads-pavements/dropped-kerbs/8
- https://www.bolton.gov.uk/roads-pavements/h-bar-markings
- https://www.bolton.gov.uk/downloads/download/331/dropped-kerbs
- https://www.bolton.gov.uk/downloads/file/6457/all-street-licences-charges-and-fees
- https://www.bolton.gov.uk/streets-travel-parking
- https://www.bolton.gov.uk/parking-permits